top of page

Service Interruption: September 28-October 4, 2024


September 28, 2024 (Saturday)

Time:

8:00 AM to 9:00 AM (1hr);4:00 PM to 5:00 PM (1hr)

Purpose:

To facilitate cutting of loops for isolation of working area;  installation of loops for energization of working area.

Areas Affected:

Portion of Cebu City & Consolacion (Agsungot, Binaliw, Cambinocot, Lanipga, Lusaran, Mabini, Paril & Panas) along portions of Agsungot Road, Binaliw Road, Brgy. Mabini Road, & Mansawa-Binaliw Road, including portions of Sitios Agbagon, Agbuacan, Agnawe, Aseotes, Baogo, Baugo, Bombil, Buatis, Bungan, Buntod, Busay, Camanse, Camansi, Campaso, Cantisang, Dagongdong, Eskwelahan, Gaang, Hagnum, Hubao, Kang-Atis, Laguna, Lintuang, Lipoton, Lower, Luton, Mansawa, Pinigturan, Proper, Riverside, Sandayong, Tag-Ube, Tagaytay, Tal-Ot, Tigib, Tuburan, Tupas, & Upper.


Time:

8:00 AM to 5:00 PM (9hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Agsungot, Cambinocot, Lanipga, Lusaran, Mabini, Paril & Panas by facilitating primary line upgrading.

Areas Affected:

Portion of Cebu City & Consolacion (Agsungot, Cambinocot, Lanipga, Lusaran, Mabini, Paril & Panas) along portion of Brgy. Mabini Road, including portions of Sitios Agbagon, Agbuacan, Aseotes, Baogo, Bombil, Buatis, Bungan, Buntod, Busay, Camanse, Camansi, Campaso, Cantisang, Dagongdong, Eskwelahan, Gaang, Hagnum, Hubao, Kang-Atis, Laguna, Lintuang, Lipoton, Luton, Pinigturan, Proper, Riverside, Sandayong, Tag-Ube, Tagaytay, Tal-Ot, Tigib, Tuburan, Tupas, & Upper.


Time:

9:00 AM to 3:00 PM (6hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Talamban by facilitating extension of primary lines (line stringing).

Areas Affected:

Portion of Cebu City (Talamban) along Minoza Street including portions of Sitio Tigbao.


Time:

8:00 AM to 12:00 PM (4hrs) CANCELLED

Purpose:

To improve the reliability of the distribution system serving Brgy. Hipodromo by facilitating primary line upgrading.

Areas Affected:

Portion of Cebu City (Hipodromo) along Camotes Road including portions of Ayala Business Park and Lexmark Tower 2.


September 29, 2024 (Sunday)

Time:

8:00 AM to 4:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Cansaga, Jugan, Nangka, Pitogo & Tayud by facilitating primary line maintenance.

Areas Affected:

Portion of Consolacion (Cansaga, Jugan, Nangka, Pitogo & Tayud) along portion of Laray Road, including portions of Sitios Sun-Ok & West Banabag, and Kaugmaran Homes, Marian Village, Redwood Subdivision, Sheena Homes Subdivision,  Sun Rise Ville Subdivision, Red Bark Treasures Devt. Corp., Globe Telecomunicaiton Inc., WT Construction Inc., Consolacion Baptist Church, & Miescor Infrastructure Development Corporation.


Time:

3:00 PM to 4:00 PM (1hr)

Purpose:

To improve the reliability of the distribution system serving Brgy. Cansaga, Lamac & Pitogo by facilitating tapping of primary lines.

Areas Affected:

Portion of Consolacion (Cansaga, Lamac & Pitogo) along portions of Central Nautical Highway & Maglasang Road, including portions of Sitios Centro, Laray, & Pagutlan, and Apas Compound, Carolino Compound, Maglasang Compound, Sumbi Compound, Legacy Homes Inc, Frontier Tower Associates Philippines Inc., Seaoil Philippines, Inc., Informatics College Cebu Inc., Consolacion Alliance Church, Innove Communications Inc., Maysprings Corporation, Pitogo Elementary School, Paraclete Learning Center, Pentecostal Missionary Church of Christ, Britech College Incorporated, Des Marketing, Softouch Property Development Corp., St. Joseph Chapel, RMB Consolacion Business Center, Arttrephils Corp., Maysprings Corp., La Consolacion Mill. Corp. M8, Bank of Phil. Island / Alfred Razon, Toplights Corporation, Sunflower Village Dev't Inc., & Unity Digital Infrastructure.


September 30, 2024 (Monday)

Time:

8:00 AM to 4:00 PM (8hrs)

Purpose:

To prevent unnecessary interruptions due to vegetation in the distribution system serving Brgy. Cabadiangan by facilitating trimming of tree branches and leaves.

Areas Affected:

Portion of Liloan (Cabadiangan) along Fatima Road including portions of Sitio Caingsid as well as Unity Digital Infrastructure.


October 1, 2024 (Tuesday)

Time:

9:00 AM to 3:00 PM (6hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Cabangahan by facilitating secondary line maintenance and voltage correction.

Areas Affected:

Portion of Consolacion (Cabangahan) along Cabangahan Road including portion of Sitio Nangka as well as RTU Land Inc.


Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Tungkop by facilitating replacement of distribution transformer.

Areas Affected:

Portion of Minglanilla (Tungkop) portions of Purok  Sambag, Tambis, Antogop, Chicos, Cacao, Kabingkoy, Gemelina, Nipa, Sambag 1, Cogon, Proper, Kalubihan, Kakaw, Molave, Sabana, Mangga Sitio's  Tulilik, Bantayan, Kskc, Bantayan, and South Boundary.


Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Greenhills by facilitating upgrading of distribution transformer.

Areas Affected:

Portion of San Fernando (Greenhills) including portions of Sitios Mohon, Topshill and SunnyHills.


Time:

9:00 AM to 3:00 PM (6hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. San Roque by facilitating rerouting of secondary lines.

Areas Affected:

Portion of Talisay City (San Roque) along Ughai II st., San Roque.


October 2, 2024 (Wednesday)

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Mambaling by facilitating reconstruction of primary lines.

Areas Affected:

Portion of Cebu City (Mambaling) along Alaska St. and Ipil Ipil St. including portions of Sitio Naba, Sitio Wang Yu, Sitio Ipil Ipil, Sitio Lawis Alaska, Sitio Abbya, Naba Home Vision Association, Ipil-Ipil Ybanez Compound Road, Share A Child Movement Inc., and Our Mother of Perpetual Help Chapel.


October 3-4, 2024 (Thursday-Friday)

Time:

10:00 PM of October 3 to 6:00 AM of October 4 (8hrs) CANCELLED

Purpose:

To prevent unnecessary interruptions due to anticipated system fault/damage in Brgy. Calamba, Guadalupe & Labangon by facilitating Hotspot Correction.

Areas Affected:

Portion of Cebu City (Calamba, Guadalupe & Labangon) along portions of Sun Valley Road & V. Rama Avenue, including portions of Sitios Camalig, Cogon, Greenland, Mahayahay, & Yumoy, and Calamba Quijano, Espina Compound, Nacar Compound, Tunito Homes Sun Valley Subdivision, & V. Rama Avenue Sun Valley Subdivision.






































bottom of page