January 18, 2025 ( Saturday)
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Dumlog by facilitating relocation of primary pole for upcoming projects. |
Areas Affected: | Portion of Talisay City (Dumlog) including portions of Sitio Baybay & Deca Homes Subdivision Phase 1. |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Apas by facilitating installation of primary pole. |
Areas Affected: | Portion of Cebu City (Apas) along Dagohoy St. including portion of Sitios Calvary Hills, Mahayahay, & San Antonio, Dotallas Compd., and Abejo Waters Corp. |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To increase the capacity of the distribution system serving Brgy. Talamban by facilitating installation of distribution transformer. |
Areas Affected: | Portion of Cebu City (Talamban) along 1256 J. Bontuyan Street including Academia De San Isidro Labrador Campesino, Inc. |
Time: | 9:00 AM to 12:00 PM (3hrs) |
Purpose: | To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Pooc by facilitating relocation of primary pole as per customer request. |
Areas Affected: | Portion of Talisay City (Pooc) along Mohon Rd. including portions of Sitio Ranger. |
January 19, 2025 (Sunday)
Time: | 9:00 AM to 1:00 PM (4hrs) |
Purpose: | To prevent unnecessary interruptions due to vegetation in the distribution system serving Brgy. Tayud by facilitating trimming of tree branches and leaves. |
Areas Affected: | Portion of Consolacion (Tayud) along portions Consolacion-Tayud Liloan Rd. including Monocrete Construction Philippines Inc. Cebu Satellite Office. |
January 21, 2025 (Tuesday)
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Cambinocot by facilitating relocation of primary pole as per customer request. |
Areas Affected: | Portion of Cebu City (Cambinocot) including Purok 2 Mahayahay. |
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Pitalo & Langtad by facilitating reconstruction of primary lines. |
Areas Affected: | Portion of San Fernando & City of Naga (Pitalo & Langtad) including portions of Casa Mira South Subdivision. |
January 22, 2025 (Wednesday)
Time: | 9:00 AM to 12:00 PM (3hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Banilad by facilitating primary line upgrading. |
Areas Affected: | Portion of Cebu City (Banilad) including portions of Maria Luisa Subdivision along Paseo Annabelle and Paseo Emilio, as well as Streetscape Residences Inc. |
Time: | 10:00 PM to 11:00 PM (1hr) |
Purpose: | To facilitate cutting of loops for isolation of working area. |
Areas Affected: | Portion of Cebu City (Kinasang‑an Pardo) along Sitio Baspas. |
January 22-23, 2025 (Wednesday-Thursday)
Time: | 10:00 PM of January 22 to 5:00 AM of January 23 (7hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Mambaling by facilitating primary line maintenance and replacement of damaged line device hardware (DS/FCO/Insulator/LBS). |
Areas Affected: | Portion of Cebu City (Mambaling) along Sitio Abbya. |
January 23, 2025 (Thursday)
Time: | 9:00 AM to 5:00 PM (8hrs) |
Purpose: | To improve the reliability of the distribution system serving Brgy. Cogon Ramos by facilitating installation of primary pole. |
Areas Affected: | Portion of Cebu City (Cogon Ramos) along Maxilom, Gen. Ave. |
Time: | 4:00 AM to 5:00 AM (1hr) |
Purpose: | To facilitate installation of loops for energization of working area. |
Areas Affected: | Portion of Cebu City (Kinasang‑an Pardo) along Sitio Baspas. |
January 24, 2025 (Friday)
Time: | 8:00 AM to 5:00 PM (9hrs) |
Purpose: | To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Greenhills by facilitating relocation of secondary pole that is affected by road widening project. |
Areas Affected: | Portion of San Fernando (Greenhills) including portions of Purok Greenfield. |