January 9, 2025 ( Wednesday)- Additional Power Interruption

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Capitol Site by facilitating installation of distribution transformer.

Areas Affected:

Portion of Cebu City (Capitol Site) along Don Mariano Cui Street including D2 Business Park Inc.

January 11, 2025 (Saturday)

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Banilad by facilitating installation of distribution transformer.

Areas Affected:

Portion of Mandaue City (Banilad) along H. Cortes St. including Excellens Inc.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Lahug by facilitating installation of primary pole.

Areas Affected:

Portion of Cebu City (Lahug) specifically GLOBE TELECOM INC.

Time:

9:00 AM to 2:00 PM (5hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Cabancalan & Casuntingan by facilitating installation of primary pole.

Areas Affected:

Portion of Mandaue City (Cabancalan & Casuntingan) including portions of Greenhills Subdivision, & Majestic Legacy Home Development Corporation.


Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Calajo-an by facilitating installation of primary pole.

Areas Affected:

Portion of Minglanilla (Calajo-an) specifically MONTECARLO REALTY & DEVT. CORPORATION.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. San Vicente by facilitating relocation of primary pole as per customer request.

Areas Affected:

Portion of Liloan (San Vicente) including portions of Purok of Limogmog Curva.

January 12, 2025 (Sunday)

Time:

8:00 AM to 4:00 PM (8hrs)

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Tayud by facilitating relocation of primary pole as per customer request.

Areas Affected:

Portion of Consolacion (Tayud) along portions of Sitio Libo, Purok 4 Orchids, After Tayud Elementary School, Linkworld Designs Unlimited Inc.

Time:

8:00 AM to 4:00 PM (8hrs)- CANCELLED

Purpose:

To improve the reliability of the distribution system serving Brgy. Babag & Bonbon by facilitating relocation of primary pole for upcoming projects.

Areas Affected:

Portion of Cebu City (Babag & Bonbon) along portions Cebu Transcentral Highway including portions of Maomawan Babag.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Camp IV , Jaclupan , Lagtang , Tabunok & To-ong by facilitating installation of primary pole.

Areas Affected:

Portion of Talisay City & Cebu City (Camp IV , Jaclupan , Lagtang , Tabunok & To-ong) along portions of Cebu-Toledo Wharf Road, Molave Ext. Street, Toledo Manipis Road, Toledo-Tabunok Road, & Zone 3 Ilang-Ilang Street, including portions of Sitios Acacia, Acasia, Badbad, Bogo, Buacao, Bugna, Burlas, Calombangan, Cambawog, Camp 5, Caolong, Caulong, Cuadra, Dike, Ibo, Ilang-Ilang, Ipil-Ipil, Kawayanan, Kemwa, Lajara, Lawis Candulawan, Luna, Lupa, Malunhaw, Manguilamon, Nangka, Proper, Quadra, Saging, Saksak, Sambagan, Sda, Sitio Hollow Block, Tabok, Tabok Sapa, Tigib, & Tungasan, and Benigno Compound, Creek Village, Harmonis Residences, Hilltop Lagtang, Hollowblock Subdivision, Kahill, Kishanta Subdivision, Labajos Compound, Sta. Catalina Subdivision, Susana Compound, & Tabay Compound.

January 14, 2025 (Tuesday)

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Apas by facilitating extension of primary lines (line stringing).

Areas Affected:

Portion of Cebu City (Apas) along portions of Wilson St., and Lower Torralba St.

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Polog by facilitating extension of primary lines (line stringing).

Areas Affected:

Portion of Consolacion (Polog) specifically at Responsible Internet Sustainability Effort Inc.

Time:

9:00 AM to 3:00 PM (6hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Kinasang‑an Pardo & Poblacion Pardo by facilitating upgrading of distribution transformer.

Areas Affected:

Portion of Cebu City (Kinasang‑an Pardo & Poblacion Pardo) along E. Sabellano St. including portions of Sitios Mahayahay I,II, Kinasang-an, Kabogohan, & Kamansi.