Service Interruption: April 27-May 3, 2024


April 27, 2024 (Saturday)

Time:

8:00 AM to 4:00 PM (8hrs)

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. San Roque & Tangke by facilitating relocation of primary pole as per customer request

Areas Affected:

Portion of Talisay City (San Roque & Tangke) along Rabaya Rd. and Washington St. including portions of Purok Purok Kalapati, Kiros, Tilapia, Maya, Barungoy, Mamsa, Ito, Swasid, Caraballas, Blue Marlin, Sitio Rattan, Tunga, Kilawan, Magay, Kimba, Mangga, Galaxy, Salavador, Sawsawan, Sambagan, Pahumay, Villa Laguna, Naya Subdivision, Tosen Foods Inc., Dito Telecommunity Corporation, & Innove Communication Inc.


Time:

9:00 AM to 3:00 PM (6hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Tinaan by facilitating installation of primary pole

Areas Affected:

Portion of City of Naga (Tinaan) specifically at Asphalt Pavement Solutions Inc.


Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Tunghaan by facilitating upgrading of distribution transformer

Areas Affected:

Portion of Minglanilla (Tunghaan) including portions of Kamalaya Residences II.


Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Lawaan III by facilitating upgrading of distribution transformer

Areas Affected:

Portion of Talisay City (Lawaan III) including portions of Pungsod, Purok Lumboy.


Time:

8:00 AM to 5:00 PM (9hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Lahug by facilitating switchgear PMS

Areas Affected:

Portion of Cebu City (Lahug) specifically at JP Morgan E-Bloc1, E-Bloc4 i1,i2,i3 and The Link Asia Premier.


Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Guadalupe by facilitating installation of distribution transformer

Areas Affected:

Portion of Cebu City (Guadalupe) specifically at Lejean & Sons Realty Corp.



April 28, 2024 (Sunday)

Time:

8:00 AM to 4:00 PM (8hrs)

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Kalubihan , Kamagayan , Sambag I & Sambag II by facilitating relocation of primary pole as per customer request

Areas Affected:

Portion of Cebu City (Kalubihan , Kamagayan , Sambag I & Sambag II) along N. Bacalso Avenue, Leon Kilat St., Sanciangko St., Osmeña Blvd., Pelaez St., P. Del Rosario St., including portions of Sitio Pailob, Tangkongan, Kawayan, Urgello, Amor, Tianggehan, Kalinaw, Kabulihan, Caimito, Aspire Homes, Sambag Central Subdiv, Arriola Subd., Mya 2 Townhomes, Villa Aznar, San Roque Village, Jd Residences, GSIS Compound, Community Developers & Const., Corp., MCD Credit Corporation, Ong Kin King Land Realty Inc., Cebu Urban Design & Dev. Corp., Tuxedo Business Suites Inc., Cebu Coliseum Complex Inc, Gaka Patuki Corporation, Globe Telecom Inc., Cebu CPA Foundation,Inc., City Central Elem. School, Bonne Realty Corporation, Golden Arches Development Corp., Southwestern University,Inc., Phinma Property Holdings Corp., Philippine Veterans Bank, Buhing Pasko Association Inc., Esperanza L. Osmena Inc., Kalubihan Barangay Hall, Joelino Realty Investment & Dev. Corp., San Antonio De Padua Chapel, Asia Consumer Value Trading Inc., SWU Alumni Foundation Inc., Golden Valley Hotel Inc., Metrobank & Trust Co. Smart Communication Inc., Classy Clothier Inc., The Superior General Of The Religious Of The Virgin Mary, Inc., Jet Development Corporation, Security Bank Savings, Cebu Central Colleges, Rose Pharmacy Inc., Pagtambayayong - A Foundation For Mutual Aid, Philippine Seven Corporation, Almurill Copy Center, Dreamfield Realty & Management Corp, ISNG. Ceb-Sanc, Inc., Pawnsafe Services Corporation, Southwestern University, Exploration Lepanto Exploration Asia Inc., Queen City Development Bank, Pacific Catv Inc., Cebu Appliance Center Inc., Mother Of Perpetual Help Chapel, La Nora Realty Dev. Corp., Mercedes Hotel, Cinco Fortunata P (Pump), Global Bank, Lihok Pilipina Foundation Inc, Asia Consumer Value Trading, Inc., Island Fry Foods Franchise Corp., Converge Ict Solution Inc., Acen Corporation, Cebu Ohana Dev'T. Corp., Sto Nino Chapel, Red Builders Construction And General Supply Corp., Veronis Inc., , Mobile Phils. Inc., Cebuview Realty Corporation, Dev. Bank Of The Phil., University Of Cebu Inc., Vantage Energy Solutions & Management Inc., Citi Appliance (Mc) Corporation & Gv Tower Hotel, Johndorf Ventures Corporation, & Voyager I.T.Solutions,Inc.,


Time:

8:00 AM to 11:00 AM (3hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Panadtaran & Tonggo by facilitating installation of line device hardware (DS/FCO/LBS)

Areas Affected:

Portion of San Fernando (Panadtaran & Tonggo) along Cebu South Rd. including portions of Purok Manatad, Tuyukon, Nangka, Avocado, Lobi, Aguila, Sitios Tapok-Tapok, Tagik, Panaghiusa, Kolasing, Kamading, Guia, Golden Gate Chicken Ranch Corporation, Brgy. Tonggo Water Works System, Barangay Tonggo Water Pump & Mun. Of San Fernando Radio Repeater.


Time:

8:00 AM to 4:00 PM (8hrs)

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Panadtaran & Tonggo by facilitating relocation of primary pole that is affected by road widening project

Areas Affected:

Portion of San Fernando (Panadtaran & Tonggo) including portions of Purok Aguila, Tuyukon, Nangka, Guia, Manatad, Avocado, Sitios Tagik, Tapok-Tapok, Kamagding, Golden Gate Chicken Ranch Corporation, Brgy. Tonggo Water Works System, Barangay Tonggo Water Pump, & Mun. Of San Fernando Radio Repeater.



April 29, 2024 (Monday)

Time:

1:00 PM to 4:00 PM (3hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Sawang Calero by facilitating removal of primary lines as requested by customer

Areas Affected:

Portion of Cebu City (Sawang Calero) Along Tupas St., including portions of Sitio Omega.


April 30, 2024 (Tuesday)

Time:

9:00 AM to 3:00 PM (6hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Tipolo by facilitating removal of distribution transformer

Areas Affected:

Portion of Mandaue City (Tipolo) Portions of Mt. Banahaw Street.


Time:

9:00 AM to 3:00 PM (6hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Pitogo by facilitating extension of primary lines (line stringing)

Areas Affected:

Portion of Consolacion (Pitogo) inlcuding portions of James Andrei Property Development Inc.


Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Busay by facilitating installation of distribution transformer

Areas Affected:

Portion of Cebu City (Busay) along Alimaong St., Nivel Hills


Time:

9:00 AM to 1:00 PM (4hrs)

Purpose:

To improve the reliability of the distribution system serving Brgy. Camputhaw by facilitating removal of distribution transformer

Areas Affected:

Portion of Cebu City (Camputhaw) Along Apitong St., specifically at Alas De Angel Hotel & Resort Corporation.


Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Vito by facilitating relocation of primary pole as per customer request

Areas Affected:

Portion of Minglanilla (Vito) Along portions of 18 De Julio & Tagaytay Road, including portions of Sitios Acoy, Camarin, Imot, Tagaytay, Teves, & Ugoy, and Montecarlo Subdivision & Victoria Heights.



May 2, 2024 (Thursday)

Time:

9:00 AM to 5:00 PM (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Cuanos by facilitating upgrading of distribution transformer

Areas Affected:

Portion of Minglanilla (Cuanos) including portions of Banga-an.



May 2-3, 2024 (Thursday-Friday)

Time:

10:00 PM of May 2 to 6:00 AM of May 3 (8hrs)

Purpose:

To increase the capacity of the distribution system serving Brgy. Poblacion by facilitating extension of primary lines (line stringing)

Areas Affected:

Portion of Liloan (Poblacion) along Cebu North Rd., including portions of Purok Mahogany & Rosal, Sitios Angelico, & Bajac.


bottom of page