September 28, 2022 (Wednesday)
Time :8:00 AM to 5:00 PM (9hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Balirong by facilitating primary line upgrading.
 Areas affected: 
 Portion of City of Naga (Balirong) along Balirong Rd. including portions of Sitio Punod.
   
September 27, 2022 (Tuesday)
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Poblacion by facilitating installation of primary pole.
 Areas affected: 
 Portion of Talisay City (Poblacion) along La Revolution St. including portion of Purok Kamunggay and Sto. Nino Aquaculture Corp.
   
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To increase the capacity of the distribution system serving Brgy. Malubog by facilitating upgrading of distribution transformer.
 Areas affected: 
 Portion of Cebu City (Malubog) including portion of Sitio Tiguib.
   
September 25, 2022 (Sunday)
Time :7:00 AM to 3:00 PM (8hrs)
 Purpose :To increase the capacity of the distribution system serving Brgy. Alang-Alang by facilitating installation of distribution transformer.
 Areas affected: 
 Portion of Mandaue City (Alang-Alang) along P. Burgos St. including Jabbe Properties Inc., and Globe Telecom Inc.
   
Time :2:00 AM to 10:00 AM (8hrs)
 Purpose :To increase the capacity of the distribution system serving Brgy. Camputhaw by facilitating extension of primary lines (line stringing)
 Areas affected: 
 Portion of Cebu City (Camputhaw) along Gorordo Ave. including Machay Agri & Trdg. Corp.
   
Time :8:00 AM to 4:00 PM (8hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Biasong & Dumlog by facilitating retensioning of primary lines and replacement of primary pole.
 Areas affected: 
 Portion of Talisay City (Biasong & Dumlog) along Burgos St. including portions of Sitios Minggoy, Pidanna, Kawayan, Zone 4 & Zone 5, Pueblo San Ricardo Subd., Palm River Subd., Raphael Homes, Talisay City Slaughter House, Prima Value Communities Inc., and Filpride Products.
   
Time :8:00 AM to 9:00 AM (1hr);  3:00 PM to 4:00 PM (1hr)
 Purpose :To facilitate cutting of loops for isolation of working area; installation of loops for energization of working area.
 Areas affected: 
 Portion of Talisay City (Dumlog) along E. Bascon St. & Burgos St. including portions of Sitios San Jose, Paglaum, Mangga, & Zone 4, Larida Ville, Azcuna Compd., Champaca Compd., Alden Compd., Arienza Land Corp. and Rell & Renn Trading Corp.
   
September 24, 2022 (Saturday)
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Tisa by facilitating replacement of primary pole.
 Areas affected: 
 Portion of Cebu City (Tisa) along Katipunan St. including portions of Sitios Manol, & Manga, and Immaculate Concepcion Chapel.
   
September 22, 2022 (Thursday)
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Pit-os & Pulangbato by facilitating rerouting of primary lines
 Areas affected: 
 Portion of Cebu City (Pit-os & Pulangbato) including portions of Sitios Kamanggahan, Pundok, Candarong, Burgos, Canumay, Centro, Kasambagan, Nawanao, Proper, & Tuburan, Villa Del Rio 2 Subd., Greenwoods Subd., Camella Homes, Brgy. Pulangbato Sports Complex, Sta. Lucia Realty & Dev Inc., and Helpmate Inc.
   
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To increase the capacity of the distribution system serving Brgy. Kinasang‑an Pardo by facilitating upgrading of distribution transformer
 Areas affected: 
 Portion of Cebu City (Kinasang‑an Pardo) along Kinasangan Extn. Rd. including portions of Sitio Lower Acacia, Rainbow Village, and Greyhound Subdivision.
   
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Tipolo by facilitating installation of primary pole
 Areas affected: 
 Portion of Mandaue City (Tipolo) along Lopez Jaena St. including portions of Sitio Allied, Digitel Telecommunications Phils Inc., San Gabriel Metal Concepts Inc., G J Industries, and Wellmade Motors And Dev Corp.
   
September 21-22, 2022 (Wednesday-Thursday)
Time :10:00 PM of September 21 to 6:00 AM of September 22 (8hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Ermita & Sto. Niño by facilitating retensioning of primary lines
 Areas affected: 
 Portion of Cebu City (Ermita & Sto. Niño) along F. Gonzales St., D. Jakosalem St., M. Briones St., Plaridel St., Quezon Blvd., & P. Burgos St. including portions of Carbon Market, Senior Citizen Park, Perlas Marketing, Unson Hardware, Tai Guan Temple Inc., Yu Kim Kee Chua & Co, Rosalins Enterprises, Pacific Star Inc., Ogy Trading Corp., Ong King King & Co.Inc., Benison Commercial Corp., Martinez Agricultural Corp., Woolbright Corp., Bayanihan Multi-Purpose Coop., Sugbu Chinese Heritage Museum Foundation Inc., Wealth Development Bank, Cebu Luneta Seafarers Center Inc., Cebu Fortune Cons Supply, BDO Unibank Inc., and Allied Banking Corp.
   
September 21, 2022 (Wednesday)
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Calamba by facilitating tapping of service entrance wire
 Areas affected: 
 Portion of Cebu City (Calamba) including portion of Sun Valley Subdivision
   
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To increase the capacity of the distribution system serving Brgy. Linao by facilitating upgrading of distribution transformer
 Areas affected: 
 Portion of Minglanilla (Linao) including portions along Cebu South Rd.
   
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To increase the capacity of the distribution system serving Brgy. Bulacao by facilitating upgrading of distribution transformer
 Areas affected: 
 Portion of Cebu City (Bulacao) along Flordeliz St. including portions of Sitios Riverside & Ufeba.
   
Time :9:00 AM to 12:00 PM (3hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Canduman by facilitating relocation of guy
 Areas affected: 
 Portion of Mandaue City (Canduman) including portion of Sitio Riverside
   
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Punta Princesa by facilitating replacement of primary pole
 Areas affected: 
 Portion of Cebu City (Punta Princesa) along Buhisan Rd. including portions of Sitio Mangga, Guadalupe Village, Pardinan Compound, Clarita Village, and Stockton Village.
   
September 20, 2022 (Tuesday)
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Talamban by facilitating relocation of primary pole as per customer request
 Areas affected: 
 Portion of Cebu City (Talamban) including portions of Sunny Hills Subd., Paglaum Village, Sunny Hills Subd. Pump, Poitiers Dolphin Haus Inc. and Cathare Inc.
   
Time :9:00 AM to 3:00 PM (6hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Panoypoy by facilitating guying correction and installation of primary pole
 Areas affected: 
 Portion of Consolacion (Panoypoy) including portions of Puroks Yellow Bells & Gumamela and Proper, Lower and Upper Panoypoy.
   
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Polog by facilitating relocation of primary pole as per customer request
 Areas affected: 
 Portion of Consolacion (Polog) including portion of Sitio Manayataya
   
Time :9:00 AM to 3:00 PM (6hrs)
 Purpose :To increase the capacity of the distribution system serving Brgy. Casuntingan by facilitating installation of distribution transformer
 Areas affected: 
 Portion of Mandaue City (Casuntingan) along portions of M.L. Quezon Avenue.
   
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To increase the capacity of the distribution system serving Brgy. Pakigne & Tungkil by facilitating extension of primary lines (line stringing)
 Areas affected: 
 Portion of Minglanilla (Pakigne & Tungkil) along Countryside Village including portions of Sitios Sto. Nino, Dapdap, San Roque & Noah, Agustina Village, Villa Feliza Subd., Villa Celina Subd., Deca Homes Subd., Minglanilla Homes, Tenese Feedmill Compd., Brgy. Tungkil Daycare Center, Tungkil National High School, BP Waterworks Inc., Prism Energy Inc., Kenrich Dev't. Corp., BNH Aquaculture Corp., Primary Properties Corp., and 8990 Housing Dev't. Corp.
   
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To increase the capacity of the distribution system serving Brgy. Sambag II by facilitating upgrading of distribution transformer
 Areas affected: 
 Portion of Cebu City (Sambag II) along Uytengsu St. including Cebu Capitol Commercial Complex Corp.
   
September 18, 2022 (Sunday)
Time :8:00 AM to 4:00 PM (8hrs)
 Purpose :To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Casili by facilitating relocation of primary pole as per customer request
 Areas affected: 
 Portion of Consolacion (Casili) including portions of Sitio Cambiohan.
   
Time :7:00 AM to 3:00 PM (8hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Talamban by facilitating rerouting of primary lines
 Areas affected: 
 Portion of Cebu City (Talamban) portion of Nasipit including University of San Carlos
   
Time :9:00 AM to 3:00 PM (6hrs)
 Purpose :To increase the capacity of the distribution system serving Brgy. Inayawan by facilitating upgrading of distribution transformer
 Areas affected: 
 Portion of Cebu City (Inayawan) including portions of White Road Inayawan, & Pollution Abatement Systems Specialist Inc.
   
Time :8:00 AM to 5:00 PM (9hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Centro by facilitating primary line maintenance
 Areas affected: 
 Portion of Mandaue City (Centro) along F.E. Zuellig Ave. including Petrogas Mktg. Corp., Mandaue City Fire Dept., Bureau Of Immigration, Mandaue City Govt/ City Health, Vantage Energy Solutions And Management Inc., Mandaue District Hospital , Centro Brgy. Hall, Land Registration Systems, Inc., and Harbor Jade Court Inc.
   
September 17, 2022 (Saturday)
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Tisa by facilitating relocation of primary pole as per customer request
 Areas affected: 
 Portion of Cebu City (Tisa) along Katipunan St. including portions of Sitios Mohon, Sunflower, Magtinabangay, Sineguelas, Calma, Dosdos, Mangga, Pilipog, & Upmora, San Agustin Heights, South Hills Subd., South Verdana Subd., Dosdos Village, Hillsview Village, Villa Elena Subd., Cabarrubias Heights, Climaco Compound, Tuada Compound, Odevillas Subd., Climaco Realty & Devt Corp., and Prima Value Communities Inc.
   
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Mambaling by facilitating relocation of primary pole as per customer request
 Areas affected: 
 Portion of Cebu City (Mambaling) along SRP Coast Rd. including Globe Telecom Inc. and Dito Telecommunity Corp.
   
Time :9:00 AM to 5:00 PM (8hrs)
 Purpose :To prevent unnecessary interruptions due to obstruction of pole in the distribution system serving Brgy. Tisa by facilitating relocation of primary pole as per customer request
 Areas affected: 
 Portion of Cebu City (Tisa) along Naya Rd. & Gold St. including portions of Sitios Mangga, Tabay Lawom, Sunflower, Kadasig, Calma, Hoya, Kalubihan, & Mansinitas, Urban Deca Homes Subd., Kadasig Subd., Lapina Compound, Mountain Breeze Subd., and 8990 Housing Dev'T Corp.
   