Logo
June 29, 2022 (Wednesday)
Time :3:00 A.M. to 4:00 A.M. (1hr)
 Purpose :To facilitate installation of loops prior to energization of working area.
 Areas affected: 
 Portion of Cebu City (Luz) along Archbishop Reyes Ave. including Unlimited Network Of Opportunities Int'L Corp., HDMF-Wtci Joint Venture, Direct Power Services Inc., Cebu Holdings Inc., Loreta Realty & Development Corp., Cebu Renful Development Corp., Loreta Towers 1 & 2 and Mandarin Hotel.
   
Time :9:00 A.M. to 4:00 P.M. (7hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Guadalupe by facilitating relocation of transformer.
 Areas affected: 
 Portion of Cebu City (Guadalupe) along portion of Andres Abellana St.
   
Time :8:00 A.M. to 4:00 P.M. (8hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Alpaco by facilitating primary line reconductoring and reconstruction.
 Areas affected: 
 Portion of City of Naga (Alpaco) along portion of Purok Asyong.
   
June 28-29, 2022 (Tuesday-Wednesday)
Time :10:00 P.M. of June 28 to 4:00 A.M. of June 29 (6hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Luz by facilitating preventive maintenance servicing of line hardwares and installation of disconnect switch.
 Areas affected: 
 Portion of Cebu City (Luz) along Archbishop Reyes Ave., P. Cabantan St. & Siquijor Rd. including portions of Sitios Abellana, Sto. Nino, San Roque, Kalinao, Lubi, San Vicente, & Nangka, and San Roque Chapel.
   
June 28, 2022 (Tuesday)
Time :9:00 A.M. to 4:00 P.M. (7hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Linao & Mohon by facilitating reconstruction of primary lines.
 Areas affected: 
 Portion of Talisay City (Linao & Mohon) along Fidel Bas St. including portions of Sitios Candaya, Bontores, Day-as & Libo, Sta.Monica Chapel, Linao Elementary School, AE International Construction & Development Corp., Pop & Sons Realty Corp., TKC Marketing Corp., Cascrete Builders Inc., Canada Cirilo A Chapel, and Sto. Nino Chapel.
   
Time :10:00 P.M. to 11:00 P.M. (1hr)
 Purpose :To facilitate cutting of loops prior to isolation of working area.
 Areas affected: 
 Portion of Cebu City (Luz) along Archbishop Reyes Ave. including Unlimited Network Of Opportunities Int'L Corp., HDMF-Wtci Joint Venture, Direct Power Services Inc., Cebu Holdings Inc., Loreta Realty & Development Corp., Cebu Renful Development Corp., Loreta Towers 1 & 2 and Mandarin Hotel.
   
June 26, 2022 (Sunday)
Time :8:00 A.M. to 4:00 P.M. (8hrs)
 Purpose :To help strengthen the distribution system from unwanted power interruptions caused by any line obstructions serving Brgy. Pitalo, we will be conducting line maintenance and upgrading of lines.
 Areas affected: 
 Portion of San Fernando (Pitalo) including portions of Sitios Kiw-kiw, Lacaron, Pajo, Upper Volta, Kalubihan, Camapog, Patag, & Mohon, Puroks Nangka, Avocado, Bugnay, Saging, Pina, Tambis Kalabasa, & Kamunggay, Amakan Village, San Roque Chapel, Pitalo Elementary School, Pitalo National High School, and Pitalo Brgy. Hall.
   
Time :8:00 A.M. to 4:00 P.M. (8hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Yati, San Vicente, Sta. Cruz, Tilhaong, San Roque & Tabla by facilitating primary line maintenance.
 Areas affected: 
 Portion of Consolacion & Liloan (Yati, San Vicente, Sta. Cruz, Tilhaong, San Roque & Tabla) along Yati Rd. including portions of Sitios Bas, Curva, Lumanoy, Tabay-Lawom, Mangga, Maylao, Candaguit, Katikoy, Lutheran, Ka-pisyong, Ilihan, Campaso, Katanoy, Ka-ino, Hillside, Libho, Balingasao, Antogop, Sandayong, Ka-Canog & Urban, Villa Karmina Subd., Hillsview Subd., El Monte Grande Subd., Eastland Estate Subd., Primavera Hills Subd., Villa Riza Subd., Villa Lorena 1 & 2 Subd., Mahogany Residences, Apao Village, Oporto Compd., Tabla Elem. School, San Roque Elem. School, Tabla Rural Water & Sanitation Association, Consolacion Water System, MCWD Water Pump, Eastland Property Ventures Inc., Legacy Homes Inc., San-Vic Traders Inc., Simona Alessia Holdings Corp. and Duros Dev’t. Corp.
   
June 25, 2022 (Saturday)
Time :9:00 A.M. to 5:00 P.M. (8hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Guindaruhan by facilitating installation of transformer.
 Areas affected: 
 Portion of Minglanilla (Guindaruhan) along Estaka St. including portions of Proper Purok 3.
   
Time :7:00 A.M. to 3:00 P.M. (8hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Mambaling by facilitating extension of primary lines.
 Areas affected: 
 Portion of Cebu City (Mambaling) along SRP Back Rd. including portion of South Road Properties, Amalfi Oasis Condominium, San Remo Oasis, Il Corso at  Citta Di Mare, DPWH Office, The Ranch Resort Inc., Mdk Anro Development Corp., Medina College Ipil Inc., Anseca Development Corp., Undina Spa Inc., Marro Mktg. Corp., Jik Realty Corp., Filinvest Land Inc., Marvir Lending Investors Corp., and SC Prestige-Multiventures, Inc.
   
Time :7:00 A.M. to 6:00 P.M. (11hrs)
 Purpose :To facilitate NGCP mandated power interruption.
 Areas affected: 
 Portion of Minglanilla (Cuanos) including portion of Sitio Banga-an. 
   
June 24, 2022 (Friday)
Time :8:00 A.M. to 5:00 P.M. (9hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Lusaran & Cambinocot  by facilitating reconductoring of primary lines. 
 Areas affected: 
 Portion of Cebu City (Lusaran & Cambinocot) including portions of Sitios Bombil, Hagnum, Pinigturan, Laguna, Kasing, Mangabon, & Proper, Purok 6, Lusaran National High School and Globe Telecom Inc.
   
Time :7:00 A.M. to 6:00 P.M. (11hrs)
 Purpose :To facilitate NGCP mandated power interruption.
 Areas affected: 
 Portion of Minglanilla (Cuanos) including portion of Sitio Banga-an.
   
June 23, 2022 (Thursday)
Time :9:00 A.M. to 5:00 P.M. (8hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Cadulawan by facilitating installation of primary pole.
 Areas affected: 
 Portion of Talisay City (Cadulawan) including portions of Vista Grande Subdivision.
   
Time :9:00 A.M. to 5:00 P.M. (8hrs)
 Purpose :To improve the reliability of the distribution system serving Brgy. Nangka by facilitating relocation of pole.
 Areas affected: 
 Portion of Consolacion (Nangka) including portions of Puroks 3 & 7.